Installation Instructions

6
6”
Eave Strut
5.1 Use double sided tape to attach the insulation roll to the eave strut allowing at least six inches of overhang.
C clamps may need to be used to temporarily maintain this connection until roof sheets are in place.
5.2 Unroll insulation to the other eave of the building allowing similar overhang. Keeping tension on the
insulation.
5.5 Install roof panels. If thermal blocks are supplied they should be installed between the insulation
and roof panels.
Note! It is important to keep the insulation under proper tension as the roof panels are installed. If excess sag
is developed and the top of the insulation is not in contact with the roof sheets condensation can occur.
If there is too much tension overcompression can occur which could diminish thermal performance.
ROOF – STEP 1. Perforating the vapor barrier
Endwall
5.2
Double sided
tape
STEP 5 — Installing insulation
5.1
5.4 Before installing roof
panels carefully trim 6”
of insulation off the
end of the facing and
wrap the facing around
the top of the
fiberglass. This helps
prevent water ‘wicking’
into the building.
Eave Strut
Eave Strut
Cut insulation
only NOT facing
6”
5.4