Installation Manual
7 Commissioning
7.1 Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure See
1. Commission the inverter. see section7.2, page47
2. Establish a connection to the user interface of the inverter.
There are three connection options available to choose
from:
• Direct connection via WLAN
• Direct connection via Ethernet
• Connection via Ethernet in the local network
see section7.3, page49
3. Log into the user interface. see section7.4, page52
4. Configure the inverter. Please note, that the personal
SMAGridGuard code for changing the grid-relevant pa-
rameters must be available after completion of the first ten
operating hours (see "Application for the
SMAGridGuard code" available at www.SMA-Solar.-
com).
see section7.5, page53
5. Ensure that the country data set has been configured cor-
rectly.
Inverter user manual
6. Make further inverter settings as needed. Inverter user manual
7.2 Commissioning the Inverter
Requirements:
☐ The AC circuit breaker must be correctly rated and mounted.
☐ A means of disconnecting the inverter from the PV array must be present.
☐ The inverter must be correctly mounted.
☐ All conductors must be correctly connected.
☐ Unused enclosure openings must be sealed tightly with sealing plugs.
7 Commissioning
SMA Solar Technology America LLC
Installation manual 47SB5.0-6.0-1SP-US-40-IA-xx-10