At the time of manufacture, siding meets or exceeds the per-
formance standards set forth in ICC-ES AC321 and has achieved
code recognition under ESR-1301, CCMC 11826-L, APA recognition
under PR-N124, and HUD recognition under HUD-MR# 1318b. For
copies of ESR-1301, call LP Customer Support at 1-800-648-6893
or go online at http://www.icc-es.org/reports/pdf_files/ICC-ES/
ESR-1301.pdf or http://www.apawood.org.
Strand Substrate panel siding with SilverTech or SmartFinish
is specifically for sheds and other outdoor structures where the
interior wall cavities will remain permanently exposed.
Minimum 6 inch clearance must be maintained between siding
and finish grade.
Siding applied adjacent to porches, patios, walks, etc. must have
a clearance of at least 1 inch above any surface.
Minimum 1 inch clearance at intersection with roof line
Apply siding in a manner that prevents moisture intrusion and
water buildup.
All exposed wood substrate must be sealed in a manner that
prevents moisture intrusion and water buildup.
LP does not recommend LP SmartSide Panel for use in ICF and
SIP assemblies. If used, LP will not warrant for Buckling and
Shrinkage. However, balance of warranty does remain intact.
DO NOT USE STAPLES
SIDING MUST NOT BE IN DIRECT CONTACT WITH MASONRY,
CONCRETE, BRICK, STONE, STUCCO OR MORTAR.
S
Store o the ground well supported, on a flat surface, under a
roof or separate waterproof covering
Keep siding clean and dry. Inspect prior to application.
G  S
Seal all gaps with a high-quality, non-hardening, paintable
sealant. Follow the sealant manufacturer’s instructions for
application.
Use a high-quality exterior sealant meeting the ASTM C920,
minimum Class 25 sealant.
S S
Strand Substrate 38 and 76 Series panel siding must be installed
on 16 inch o.c. framing only. When installing on 24 inch o.c.
framing, 190 Series panel siding is required.
In all installations over masonry or concrete walls, the wall shall
be furred out and open at the top and bottom of the wall to allow
for convective ventilation between framing spaced 16 inch o.c. The
framing shall be of adequate thickness to accept 1-1/2 inches of nail
penetration. A properly installed breathable water-resistive barrier
is required between the siding and masonry or concrete walls.
S W-R B
LP strongly recommends the use of a secondary water-resis-
tive barrier behind all LP SmartSide siding. A properly installed
water-resistive barrier provides a second line of defense to
incidental moisture behind the siding.
The LP SmartSide limited warranty does not expressly or im-
plicitly cover water penetration. LP does not assume responsi-
bility for any water penetration.
Sheds and other accessory structures that are not heated or
cooled do not require a secondary water-resistive barrier if
exempt by applicable building codes.
M
Moisture control and water vapor control are critical elements
of proper housing design. Check your local building codes for
application procedures for handling moisture and water vapor
in your area.
When using wet blown cellulose insulation, the insulation
must not be in direct contact with the siding and it must be
allowed to dry a minimum of 24 hours or longer if specified by
the insulation manufacturer.
As with all wood products, do not apply engineered wood
siding to a structure having excessive moisture conditions such
as drying concrete, plaster or wet blown cellulose insulation. If
such conditions exist, the building should be well ventilated to
allow it to dry prior to the application of the siding.
Siding must not be applied to green or crooked structural
framing members. Do not apply siding over rain-soaked or
buckled sheathing materials.
Gutters are recommended for control of roof water run o.
All openings must be properly sealed or flashed in a manner
that prevents moisture intrusion or buildup. Several examples
that accomplish this are shown on the following pages.