Energy Storage System “IJ1001SNBT” Set the connecting box and conduit Wiring 4 position bellow.
Energy Storage System “IJ1001SNBT” Set the connecting box and conduit Tie the cables follow the bellow instruction and add some of magnetic core.
Energy Storage System “IJ1001SNBT” Set the connecting box and conduit Set the front door then Completed.
Energy Storage System “IJ1001SNBT” On site software update Because of preinstalled software in factory, normally it is not required to install any software. But in some cases, software update may be required on site. On site software update procedure is as follows. 1. 2. 3.
Energy Storage System “IJ1001SNBT” Commissioning CAUTION : Connect the energy storage system to the electrical utility grid only after receiving prior approval from the utility company. CAUTION : Be aware that only qualified personnel should must connect the energy storage system to the electrical utility grid. CAUTION : Ensure that all AC and DC wiring is correct. Ensure that none of the AC and DC wires are pinched or damaged.
The Energy Storage System Activation Connecting to the Internet 1. Confirm that there is a home router with wireless LAN working in the residence. 2. Connect with the home router using WPS. Please follow a procedure below. (as same as normal WPS operation) 1. Turn ON the circuit protector located behind of the energy storage server. ( RED ARROWS ) 2. Wait for booting the Energy Storage Server. 3. Push WPS button on the home router. 4.
The Energy Storage System Activation Activating Energy Storage System for Field Trial 1. Turn ON the Energy Storage Server and wait for boot. 2. Confirm that the Energy Storage System is already connected to the Internet. (WPS is already done) 3. Access to the cloud server to register the Energy Storage System, using Installer Web Application. Installer Web Application is the same one for HEMS Gateway. Please follow a procedure below. (as same as one for HEMS Gateway) 1. Login to the installer application.
2. Input SI Setup ID. Input SI Setup ID Then push OK 3. Confirm SI Setup ID.
4. Go to registration process of Energy Storage System (called “Battery” in this application). Push “Register New Gateway” 5. Scan barcode which is labeled on transparent acrylic board inside the outer enclosure. If there is no barcode scanner, you can input barcode directly.
6. Confirm that Energy Storage System is powered on (called “Battery” in this application).
7. After waiting for a while※, it is successfully registered. Confirm that Energy Storage System which is newly registered is listed in Registered Gateways and its status is online. ※ If Energy Storage System is already booted and ready, it is around 10-15 seconds. But if you supply power in step6, it takes around 5 minutes.
APPENDIX 68
Energy Storage System “IJ1001SNBT” How to Power ON/OFF the Energy Storage System Power ON : Turn ON the circuit protector located behind of the energy storage server inside the outer enclosure.
Energy Storage System “IJ1001SNBT” Indicator LEDs Energy Storage Server WiFi Charge Discharge or WiFi Charge Discharge or WiFi Charge Discharge Inverter There are five inverters in the outer enclosure. Each inverter has a LED indicator at the center of side panel of one. Startup LED Operation (beginning of discharge): One minute after DC power is first applied to the inverter, six short green blinks indicate a successful inverter startup sequence.