Installation Instructions

22
When splicing two pieces of Cover Strip, allow for a minimum
overlap of four inches (4"). After properly rolling the entire
Cover Strip, install a six inch (6") piece of Tape Flashing over
any T-Joints. Seal all exposed edges with Rubber Caulk.
ROOFKIT MEMBRANE TO
SHINGLE TRANSITION
When installing a RoofKit Rubber Roong Membrane system
with a tie-in to an existing shingle roof, remove three (3)
courses of shingles.
Adhere the membrane onto the sloped roof deck. Peel the top of
the membrane back and apply a bead of Waterstop between the
membrane and the deck. Nail the top of the membrane every six
inches (6") and install the shingles over the RoofKit membrane.
See Figure 19.
Keep the bottom course of shingles a minimum of four inches
(4") above the roof angle change. To adhere the bottom course
of loose shingle tabs to the membrane, lift each tab and apply a
bead of Rubber Caulk.