Owner's manual

2
Prestige TriMax Boiler Manual Addendum
The drain line materials must be an ap-
proved material by the authority having
jurisdiction. In absence of such authority,
PVC and CPVC piping must comply with
ASTM D1785 or D2845. The cement and
primer used on the piping must comply
with ASME D2564 or F493. For installa-
tions in Canada, use CSA or ULC certi-
fied PVC or CPVC pipe, fittings and
cement/primer.
8. Continue the pipe from the drain assembly
to a floor drain or condensate pump.
When selecting and installing a condensate
pump, ensure the pump is approved for use
with condensing boilers and furnaces. The
pump should be equipped with an overflow
switch to prevent property damage from
potential condensate spillage.
9. The PRESTIGE will typically produce a con-
densate that is considered slightly acidic
with a pH content below 3.0. Install a neu-
tralizing filter if required by authority hav-
ing jurisdiction.
The condensate drain must remain filled
and unobstructed and allow unrestricted
flow of condensate. The condensate
should not be subject to conditions where
freezing could occur. If the condensate is
subjected to freezing or becomes ob-
structed , it can leak, resulting in potential
water damage to the boiler and surround-
ing area.
NOTICE
CAUTION
NOTICE
Flexible Tubing
(or 3/4 PVC/
CPVC Piping
to Drain)
Compression
Nut with Rubber Seal
Fill Plug
with Vaccum
Break Port
Condensate
Drain Assembly
Plastic Ball
(Not shown)
Retaining Nut
Place the Metal Washer
and (2) Rubber Gaskets
in this Order for Proper
Seal.
Fig. 14: Condensate Drain Assembly