3.2.2. Timing a CLOSE-OPEN Operation Using Contact Channel #1
The CLOSE-OPEN operation of a breaker simulates a condition where a breaker is closed on a
fault. There are three options when timing a CLOSE-OPEN operation:
1. Contact #1 CLOSE
The CT-7500 S2 will initiate a CLOSE operation. The open operation is then initiated after
contact channel #1 is closed. This option closes simulates the breaker closing on a fault
condition in the field.
2. Set DELAY
A delay from 10 to 500 ms can be set between the CLOSE command and the OPEN
command. The CT-7500 S2 will initiate the CLOSE operation and start the delay counter.
The OPEN operation will be initiated when the delay time has elapsed.
3. No DELAY
Both the CLOSE and OPEN commands are initiated by the CT-7500 S2 simultaneously.
The OPEN coil is energized when the OPEN auxiliary switch makes.
Follow the steps below to time a CLOSE-OPEN operation:
a. Start from the “START-UP” menu:
Press the [1] key (TIME BRKR).
b. The following screen will be displayed:
Press the
[1] key (NO).
c. The following screen will be displayed:
Press the [1] key (WINDOW = 1 SEC).
TIMING WINDOW:
1. WINDOW = 1 SEC
2. WINDOW = 10 SEC
3. WINDOW = 20 SEC
INSERTION RESISTOR?
1. NO
2. YES
1. TIME BRKR 02/22/11
2. GET RSLT 08:09:10
3. SETUP
4. DIAGNOSTICS