User manual

22
2 E-Stop
7-INSTALLATION AND SET-UP (continued)
7.7 Preliminary Electric Check-Out
Before connecting the machine to the mains please
carry out the following operations:
- Make sure that the socket is provided with a
ground protection circuit and that both the mains
voltage and frequency meet the indications on the
name plate of the machine.
- Check that the connection of the machine to the
mains meets the provisions of law and/or the
safety regulations in your country.
- Installed power = 0,620 kW
- Connect the power cable (A
) of the control board
to an electric socket c
- Standard power supply (See Speci cations).
7.8 Check-Out Phases
(For Three-Phases Only)
Procedure to be followed in order to connect correctly
the position of the phases:
- Set the main switch 1 in ON (I) position
(Figure 7-23).
- Check that safety guard panels are clearly shuts;
- Release the emergency stop push buttons rotating
them clockwise (Figure 7-24).
- Push the AUXILIARIES button 3;
- Push the RESET button 4;
- Push the START button 5;
(Figure 7-25).
Check the rotation direction of the side drive belts. In
case of wrong direction of rotation operate as follows:
- Push the STOP (O) button 6 and disconnect the
plug (Figure 7-26).
- Invert two phases on the terminals of the plug;
- Repeat the above mentioned procedure.
800rf-NA
2012 March
A
3
1
5
6
4
Figure 7-23
Figure 7-22
Figure 7-25
Figure 7-26
Figure 7-24
2