1.0 Introduction
1.1 About This Document
1.2 Shipping and Receiving
1.3 Assembly
1.4 The Millennium - A Description
2.0 General Description
3.0 Installation Instructions
3.1 Space Requirements
3.2 Foundations and Anchoring
3.3 General Erection Procedure
3.4 Ductwork
3.5 Ladder and Handrail Assembly
3.6 Electrical Controls and Wiring
3.7 Compressed Air Connections
3.8 Bag, Cage and Venturi Assembly, and Pulse Pipe Installation
3.9 Roof Doors
3.10 Gauge Installation
3.11 Explosion Vent Installation
3.12 Hopper Discharge Device
4.0 Initial Startup Instructions
4.1 Preparation For Start Up
4.2 Timer Control
4.3 Pressure Demand Control
5.0 Principles of Operation
6.0 Maintenance
6.1 Daily
6.2 Monthly
6.3 Six Months
7.0 Troubleshooting
7.1 High Pressure Drop Reading
7.2 Visible Discharge
7.3 Insufficient Hood Control
7.4 Fabric Bag Problems
8.0 Spare Parts
9.0 Equipment Characteristics, Operating Weights,
and Shipping Weights
Millennium
®
Pulse-Jet Fabric Dust Collectors
I
nstallation, Operation, and Maintenance Instructions
1.0 Introduction
1.1 About This Document
This document contains the information necessary to properly
receive, assemble, install, operate, and maintain the Millennium
dust collector. The purchaser, installer, and operator of the
Millennium MUST read this document in its entirety prior to
receipt and operation of the equipment.
CAUTION: These instructions are specific to the Millennium dust
collector. All ancillary tasks including, but not limited to, electrical and
mechanical work, equipment handling and safety procedures must be
performed in accordance with industry accepted practice and all
relevant local and federal codes.
1.2 Shipping and Receiving
The Millennium modules are packaged for domestic transit and
shipped FOB factory.
Obtain the original purchase order, the product drawing that was
submitted for the order, and a copy of the Bill of Lading along with
any other shipping papers. Upon receipt of the Millennium, these
documents should be used to ensure the correct modules/assemblies
have been received.
Complete the following steps upon receipt of the Millennium:
Inspect the shipment and all associated documentation. Notify
the carrier immediately if there is any damage to the shipment,
or a discrepancy in the shipping papers.