Instruction Manual
31 
Table 4 - C Cabinet Unit Clearances 
Location 
Unit Size 
16-25 and 30 tons 
Front - 
(Controls Side) 
48” 
Back - (Outside Air) 
48” 
*Left Side 
*21” 
Right Side 
60” 
Top 
Unobstructed 
*Units  with  a  water-cooled  condenser  or 
chilled  water  coil  require  48”  of  clearance 
on the left side for service access. 
Figure 2 - RN Series A, B and C Cabinet, 
6-25 and 30 tons 
Table 5 - D Cabinet Unit Clearances 
Location 
Unit Size 
26 and 31-70 tons 
Front - 
(Controls Side) 
48” 
Back - (Outside Air) 
48” 
*Left Side 
*48” 
*Right Side 
*70” 
Top 
Unobstructed 
*Right  and  left  side  unit  clearances  are 
interchangeable on units  that do not have 
hydronic  heating.  Units  with  hydronic 
heating  require  70”  right  side  access  for 
service. 
Figure 3 - RN Series D Cabinet, 
26, 31-50, 60 and 70 tons 
Table 6 - E Cabinet Unit Clearances 
Location 
Unit Size 
55, 65 and 75-140 
tons 
Front - 
(Controls Side) 
60” 
Back - (Outside Air) 
48” 
Left Side 
72” 
Right Side 
72” 
Top 
Unobstructed 
Figure 4 - RN Series E Cabinet, 
55, 65 and 75-140 tons 
Setting the Curb 
Make openings in roof decking large enough 
to allow for duct penetration and workspace 
only.  Do  not  make  openings  larger  than 
necessary. Set the curb to coincide with the 
openings. Make sure the curb is level. Unit 
must  be  level  in  both  horizontal  axes  to 
support  the  unit  and  reduce  noise  and 
vibration. 