Step 4: Remove the fan  blades and replace 
the pitch pins 
Figure 39 - Pin Groove Location 
Figure 40 - Pitch Pin Location 
Figure 41 - Example Pitch Pin 
Step 5: Replace the fan blades with the pitch 
pin  of  the blade  in the same groove  and 
reassemble the fan. 
Replace  the  blades  and  assemble  the  fan 
making  sure  to  place  the  blades  in  their 
previous  blade  sockets,  to  match  up  the 
previous orientation of hub plate casings and 
to  replace  any  balancing  weights  in  their 
previous locations. Tighten bolts in a cross 
pattern to 6.7 ft-lbs. of torque. 
Step 6: Install the fan in the unit. 
After placing the fan on the shaft, place the 
key in the shaft, make sure the screw on the 
bushing is  aligned over the key  and then 
tighten the screw to 9 ft-lbs torque. 
Filters 
Do not  operate the  unit without  filters  in 
place. Unit should  be  checked  for correct 
filter placement during startup. Operation of 
the equipment without filters will result in a 
clogged evaporator coil. 
Adjusting Refrigerant Charge 
Adjusting the charge of a system in the field 
must  be  based on  determination of  liquid 
sub-cooling and evaporator superheat. On a 
system  with  a  TXV  liquid  sub-cooling  is 
more  representative  of  the  charge  than 
evaporator superheat but both measurements 
must be taken. 
Pin Groove 
Pitch Pin 
Before  completing  startup  and 
leaving the unit a complete operating 
cycle  should  be  observed  to  verify 
that  all  components are  functioning 
properly. 
   CAUTION  