Installation Instructions
Table Of Contents
- Installation & Commissioning Handbook Vol. 1
- RECORD OF CHANGES
- TABLE OF CONTENTS
- SECTION 1 ANTENNA INSTALLATION PROCEDURE
- 1 Civil Work Checks
- 2 Localizer Antenna System Assembly
- 3 Glidepath antenna system assembly/towers 10m and 15m
- 4 Near field monitor
- 5 Marker beacon installation antenna assembly
- SECTION 2 SHELTER INSTALLATION
- 1 General
- 2 Mechanical installation LLZ/GP
- 3 Electrical Installation LLZ/GP
- 4 Mechanical Installation Marker Beacon
- 5 Electrical installation marker beacon
- 6 Remote Control Connections (TWR)
- SECTION 3 ANTENNA SYSTEMS ADJUSTMENTS PROCEDURE
- 1 NM 3522 6 elements antenna system adjustments - LLZ
- 1.1 Mechanical alignment of antenna array
- 1.2 Electrical measurements
- 1.3 Course sector width adjustment
- 1.4 Monitor combining unit (MCU) adjustments
- 1.5 Near field monitor adjustments
- 1.6 DC-Loop adjustment and testing
- 2 NM 3523B 12 Elements antenna system adjustments - LLZ (Single frequency)
- 3 NM 3524 12 Elements antenna system adjustments - LLZ (Dual frequency)
- 3.1 Mechanical alignment of antenna array
- 3.2 Electrical measurements
- 3.2.1 CSB and SBO cables
- 3.2.2 CSB/SBO phasing
- 3.2.3 Antenna cable lengths (Electrical phase equality)
- 3.2.4 Antenna pair phasing
- 3.2.5 Phase and amplitude transfer measurement
- 3.2.6 Antenna return loss
- 3.3 Course sector width adjustment
- 3.4 Monitor combining unit (MCU) adjustments
- 3.5 Near field monitor adjustments
- 3.6 DC-Loop adjustment and testing
- 4 NM 3525 24 Elements antenna system adjustments - LLZ
- 4.1 Mechanical alignments of antenna array
- 4.2 Electrical measurements
- 4.3 Course sector width adjustments
- 4.4 Monitor combining unit (MCU) adjustments
- 4.5 Near field monitor adjustments
- 4.6 DC-Loop adjustment and testing
- 5 NM 3526 16 Elements antenna system adjustments - LLZ
- 5.1 Mechanical alignments of antenna array
- 5.2 Electrical measurements
- 5.3 Course sector width adjustment
- 5.4 Monitor combining unit (MCU) adjustments
- 5.5 Near field monitor adjustments
- 5.6 DC-Loop adjustment and testing
- 6 NM 3543 Null reference antenna system adjustments - Glide path
- 6.1 Mechanical alignment of mast and antennas
- 6.2 Electrical measurements
- 6.3 CSB/SBO Phasing and sector width adjustment
- 6.4 Monitoring combining unit (MCU) adjustments
- 6.5 Location of near field antenna position
- 7 NM 3544 Sideband reference antenna system adjustment - Glide path
- 7.1 Mechanical alignment of mast and antennas
- 7.2 Initial electrical measurements
- 7.3 CSB/SBO Phasing
- 7.4 Sector width adjustment
- 7.5 Monitor combining unit (MCU) adjustments
- 7.6 Location of near field antenna position
- 7.7 Antenna distribution unit (ADU) phase and amplitude check
- 8 NM 3545 M-Array antenna system adjustments - Glide path
- 8.1 Mechanical alignment of mast and antennas
- 8.2 Initial electrical measurements
- 8.3 CSB/SBO Phasing
- 8.4 Sector width adjustment
- 8.5 Monitor combining unit (MCU) MOA 338D adjustments
- 8.6 Location of near field antenna position
- 8.7 Antenna distribution unit (ADU) DIA 346A phase and amplitude check
- 9 NM 3561 Single antenna system adjustments - MKR
- 10 NM 3562 Dual antenna system adjustments - MKR
- 1 NM 3522 6 elements antenna system adjustments - LLZ
- SECTION 4 TEST AND ADJUSTEMENTS
- 1 Tests and adjustments LLZ/GP
- 1.1 Configuration Settings
- 1.2 Transmitter Alignments and Calibration
- 1.3 Antenna System Adjustments
- 1.4 Monitor Alignment and Calibration.
- 1.5 Monitor Alarm Setting Procedure
- 1.6 Maintenance Limit Adjustments
- 1.7 Adjustment points
- 2 Tests and adjustments marker beacon
- 1 Tests and adjustments LLZ/GP
- SECTION 5 GROUND COMMISIONING REFERANCE DOCUMENTS
- SECTION 6 APPENDIX
- Diagram 1 Relative SBO vs CS Width, NM3522.
- Diagram 2 Relative SBO vs CS Width, NM3523B.
- Diagram 3 Relative SBO vs CS Width, NM3524.
- Diagram 4 Relative SBO vs CS Width, NM3525.
- Diagram 5 Relative SBO vs CS Width, GP antenna systems.
- Diagram 6 GP angle vs relative antenna height, NM3545.
- Diagram 7 GP angle vs relative antenna height, NM3544.
- Diagram 8 GP angle vs relative antenna height, NM3543.
- SECTION 1 ANTENNA INSTALLATION PROCEDURE
Measure and record phase/amplitude for upper antenna transfer signals. Then determine if
one of the monitor cables must be trimmed in order to comply with phase tolerance for the set
of cables.
Tolerance: ±1°.
Amplitude tolerance: ±1.0 dB. If the amplitude tolerance is exceeded something might be
wrong in the Antenna monitor circuit or connector/cable.
Record final result in Ground Commissioning Record.
7.2.4 Antenna return loss
Utilise a vector voltmeter or network analyser in a test set-up Figure 7-3. Measure return loss
for each Antenna.
Measure and record in Ground Commissioning Record the return loss value for each Antenna
including antenna cable.
Tolerance: 20 dB minimum
.
Figure 7-3 Antenna return loss measurement set-up.
7.3 CSB/SBO Phasing
7.3.1 CSB and SBO cables
The CSB and SBO cable between NM3531 cabinet and MCU must be of equal electrical
length. Utilise a vector voltmeter or network analyser in a test set-up as in Figure 7-1.
Measure open cable return phase for each cable.
Refer to CSB cable as zero phase and measure the return phase for the SBO cable. The
cable pair must be matched within ±3.0° return phase, equal to ±1.5° true phase.
20dB
AB
VECTOR VOLTMETER
From cabinet
CSB BNC o/
p
DIR. COUPL.
Antenna cable under test
Antenna