Installation Instructions
Table Of Contents
- Installation & Commissioning Handbook Vol. 1
- RECORD OF CHANGES
- TABLE OF CONTENTS
- SECTION 1 ANTENNA INSTALLATION PROCEDURE
- 1 Civil Work Checks
- 2 Localizer Antenna System Assembly
- 3 Glidepath antenna system assembly/towers 10m and 15m
- 4 Near field monitor
- 5 Marker beacon installation antenna assembly
- SECTION 2 SHELTER INSTALLATION
- 1 General
- 2 Mechanical installation LLZ/GP
- 3 Electrical Installation LLZ/GP
- 4 Mechanical Installation Marker Beacon
- 5 Electrical installation marker beacon
- 6 Remote Control Connections (TWR)
- SECTION 3 ANTENNA SYSTEMS ADJUSTMENTS PROCEDURE
- 1 NM 3522 6 elements antenna system adjustments - LLZ
- 1.1 Mechanical alignment of antenna array
- 1.2 Electrical measurements
- 1.3 Course sector width adjustment
- 1.4 Monitor combining unit (MCU) adjustments
- 1.5 Near field monitor adjustments
- 1.6 DC-Loop adjustment and testing
- 2 NM 3523B 12 Elements antenna system adjustments - LLZ (Single frequency)
- 3 NM 3524 12 Elements antenna system adjustments - LLZ (Dual frequency)
- 3.1 Mechanical alignment of antenna array
- 3.2 Electrical measurements
- 3.2.1 CSB and SBO cables
- 3.2.2 CSB/SBO phasing
- 3.2.3 Antenna cable lengths (Electrical phase equality)
- 3.2.4 Antenna pair phasing
- 3.2.5 Phase and amplitude transfer measurement
- 3.2.6 Antenna return loss
- 3.3 Course sector width adjustment
- 3.4 Monitor combining unit (MCU) adjustments
- 3.5 Near field monitor adjustments
- 3.6 DC-Loop adjustment and testing
- 4 NM 3525 24 Elements antenna system adjustments - LLZ
- 4.1 Mechanical alignments of antenna array
- 4.2 Electrical measurements
- 4.3 Course sector width adjustments
- 4.4 Monitor combining unit (MCU) adjustments
- 4.5 Near field monitor adjustments
- 4.6 DC-Loop adjustment and testing
- 5 NM 3526 16 Elements antenna system adjustments - LLZ
- 5.1 Mechanical alignments of antenna array
- 5.2 Electrical measurements
- 5.3 Course sector width adjustment
- 5.4 Monitor combining unit (MCU) adjustments
- 5.5 Near field monitor adjustments
- 5.6 DC-Loop adjustment and testing
- 6 NM 3543 Null reference antenna system adjustments - Glide path
- 6.1 Mechanical alignment of mast and antennas
- 6.2 Electrical measurements
- 6.3 CSB/SBO Phasing and sector width adjustment
- 6.4 Monitoring combining unit (MCU) adjustments
- 6.5 Location of near field antenna position
- 7 NM 3544 Sideband reference antenna system adjustment - Glide path
- 7.1 Mechanical alignment of mast and antennas
- 7.2 Initial electrical measurements
- 7.3 CSB/SBO Phasing
- 7.4 Sector width adjustment
- 7.5 Monitor combining unit (MCU) adjustments
- 7.6 Location of near field antenna position
- 7.7 Antenna distribution unit (ADU) phase and amplitude check
- 8 NM 3545 M-Array antenna system adjustments - Glide path
- 8.1 Mechanical alignment of mast and antennas
- 8.2 Initial electrical measurements
- 8.3 CSB/SBO Phasing
- 8.4 Sector width adjustment
- 8.5 Monitor combining unit (MCU) MOA 338D adjustments
- 8.6 Location of near field antenna position
- 8.7 Antenna distribution unit (ADU) DIA 346A phase and amplitude check
- 9 NM 3561 Single antenna system adjustments - MKR
- 10 NM 3562 Dual antenna system adjustments - MKR
- 1 NM 3522 6 elements antenna system adjustments - LLZ
- SECTION 4 TEST AND ADJUSTEMENTS
- 1 Tests and adjustments LLZ/GP
- 1.1 Configuration Settings
- 1.2 Transmitter Alignments and Calibration
- 1.3 Antenna System Adjustments
- 1.4 Monitor Alignment and Calibration.
- 1.5 Monitor Alarm Setting Procedure
- 1.6 Maintenance Limit Adjustments
- 1.7 Adjustment points
- 2 Tests and adjustments marker beacon
- 1 Tests and adjustments LLZ/GP
- SECTION 5 GROUND COMMISIONING REFERANCE DOCUMENTS
- SECTION 6 APPENDIX
- Diagram 1 Relative SBO vs CS Width, NM3522.
- Diagram 2 Relative SBO vs CS Width, NM3523B.
- Diagram 3 Relative SBO vs CS Width, NM3524.
- Diagram 4 Relative SBO vs CS Width, NM3525.
- Diagram 5 Relative SBO vs CS Width, GP antenna systems.
- Diagram 6 GP angle vs relative antenna height, NM3545.
- Diagram 7 GP angle vs relative antenna height, NM3544.
- Diagram 8 GP angle vs relative antenna height, NM3543.
- SECTION 1 ANTENNA INSTALLATION PROCEDURE
1250$5&
,167580(17/$1',1*6<67(0
,167$//$7,21&200,66,21,1*+$1'%22.
1DYLD$YLDWLRQ$6
Adjust the jumper settings in P2++ and potmeters R338++ until the voltage is 240mV at
TP23++
.
Figure 1-7 Alternative jumper settings of P2++.
Turn off the equipment and remove the extender card. Set the MF12xx in its correct position.
Turn on the transmitters.
Adjust the RF level potensiometer on the front of MF12xx until the monitor gives a RF level
reading of 3.0V.
Repeat above for all monitor channels.
1.4.3 AGC Time Adjustment
Turn on the transmitters.
Make a note of the AGC voltages on TP 1,2,3 and 4 on MF12xx.
Turn off the transmitters.
Adjust the AGC TIM potmeter on the front of MF12xx until the AGC voltage (TP1,2,3 or 4) is
the same as with a nominal RF input.
Do this for all four monitor channels on all of the MF12xx modules in the system.
This ensures fast response from the monitors.
1.4.4 SDM Adjustment
Adjust the SDM potmeter on the front of MF12xx until the monitors reads 40.0/80.0%SDM +/-
0.1%SDM.
1.4.5 DDM Adjustment
Measure and note down the DDM values from the MCU and NF antenna with help of the Field
Test Set.
Set the Nominal values for each channel to the measured values with help of the RMM Pro-
gram.