Installation Instructions

Table Of Contents
MTU Instruction
for Actaris Dattus Gas Meters
Supplies and Tools Required
See Publication 471-2000, General
Installation and Wiring Guidelines for a
complete list of recommended tools and
supplies for MTU Installation.
Installation Procedure
Step 1 - Select a mounting location for
the MTU that will allow optimum signal
transmission, and install any needed
wiring. Be sure to follow all General
Installation and Wiring Guidelines as
outlined in Publication 471-2000.
Step 2 Connect the MTU cable to the
Dattus Pulse Ouput cable according to
the table below.
MTU Cable
Dattus Pulse Output
Cable
Red Red (Channel 1 +)
Black Green (Channel 1 -)
White Green (Channel 1 -)
Step 3 – Make a final visual check of the
wiring from the MTU to the meter. Verify
that the cable routing is neat, secure and
professional.
Step 4 – Once installation and wiring are
complete, program the MTU using the
STAR Programmer Software and your
MTU Programmer.
Page 196