Operating instructions

630140_1XFIRE_1200_GB_Manual_Remotion
Note:
THERE ARE A FEW THINGS TO CONSIDER BEFORE INSTALLATION
• Cavity Dimensions and Clearances
MUST be installed 100mm minimum off the floor or nearest horizontal surface.
• Coupling of flue to fire
• Coupling of gas lines to fire
• Fixing the fire to cavity
• Gas pipe placement to the front left of the cavity.
• Before installation, ensure that the local distribution conditions (identification of the type
of gas and pressure) and the adjustment of the appliance are compatible.
The sequence in which it is desired to undertake these tasks may vary upon the individual
installation that is required. Please read these instructions fully before proceeding with the
installation. Leave unpacking and installation of the stone frame (facia) until the fireplace
has been commissioned, to avoid damage to the facia panels.
Recommended Installation Process:

The following diagram illustrates the steps required to install your gas fire, and the trades
required at each stage.
Builder
1.ConstructFrame(Section1.0to6.0)
Gasfitter
4.InstallFlue+FlueRestrictorifrequired(Section12.0to13.0)
5.Testfireandverifyflamepatternisacceptable
6.Coverupfireusingpackaging(Section17.0)
Gasfitter
2.InstallGasPipe(Section7.0to8.0)
3.InstallFire(Section9.0to11.0)
Ensurethatyouleaveagapbetweenthestudworkandthefire
chassistoacceptthewallliningifapplicable.
Builder
7.Clad/linechimneybreast
Gasfitter
8.CommissiontheGasFire(Section18.0)