User manual

Table Of Contents
60 Copyright © Acronis International GmbH, 2002-2016
In the During the day execute the task... area, select one of the following:
Once at: <...>
Set up the time at which the task will be run once.
Every: <...>
From: <...> Until: <...>
Set up how many times the task will be run during the specified time interval.
For example, setting the task frequency to Every 1 hour From 10:00:00 AM
Until 10:00:00 PM allows the task to be run 13 times from 10 AM to 10 PM
during one day.
In the Effective... area, set the following settings:
From: <...>
Set up a date when this schedule will be enabled (an effective date). If this
check box is cleared, the task will be started on the nearest day and time you
have specified above.
To: <...>
Set up a date when this schedule will be disabled. If this check box is cleared,
the task will be run for an indefinite number of days.
If one or more task launches were missed while the machine was powered off, the software tries to
create a backup at the machine startup. If you do not need this extra backup, clear the If the
machine is turned off, run missed tasks at the machine startup check box.
All the settings you made are displayed in the Result field at the bottom of the window.
Examples
"Simple" daily schedule
Run the task every day at 6PM.
The schedule's parameters are thus set up as follows.
1. Every: 1 day(s).
2. Once at: 06:00:00 PM.
3. Effective:
From: not set. The task will be started on the current day, if it has been created before 6PM. If
you have created the task after 6 PM, the task will be started for the first time on the next day at
6 PM.
To: not set. The task will be performed for an indefinite number of days.
"Three-hour time interval lasting for three months" schedule
Run the task every three hours. The task starts on a certain date (say, September 15, 2009), and ends
after three months.
The schedule's parameters are thus set up as follows.
1. Every: 1 day(s).
2. Every: 3 hours
From: 12:00:00 AM (midnight) Until: 09:00:00 PM - thus, the task will be performed 8 times a
day with a 3 hour time interval. After the last daily recurrence at 9 PM, the next day comes and
the task starts over again from midnight.
3. Effective:
From: 09/15/2009. If September 15, 2009 is the current date of the task's creation and, say,
01:15 PM is the task's creation time, the task will be started when the nearest time interval