The obvious way is to add five simple schedules. If you spend one minute for examination, you can
think out a more optimal way. As you can see, the time interval between the first and the second
task's recurrences is 4 hours, and between the third, fourth and fifth is 2 hours. In this case, the
optimal way is to add two schedules to the task.
First daily schedule
1. Every: 3 day(s).
2. Every: 4 hours.
From: 08:00:00 AM Until: 12:00:00 PM.
3. Effective:
From: 09/20/2009.
To: not set.
Second daily schedule
1. Every: 3 day(s).
2. Every: 2 hour(s).
From: 03:00:00 PM Until: 07:00:00 PM.
3. Effective:
From: 09/20/2009.
To: not set.
5.2. Weekly schedule
Weekly schedule is effective in Windows and Linux operating systems.
To specify a weekly schedule
In the Schedule area, select the appropriate parameter as follows:
Every: <...> week(s) on:
<...>
Specify a certain number of weeks and the days of the week you want the
task to be run. For example, with the Every 2 week(s) on Mon setting, the
task will be performed on Monday of every other week.
In the During the day execute the task... area, select one of the following:
Once at: <...> Set up the time at which the task will be run once.
Every: <...>
From: <...> Until: <...>
Set up how many times the task will be run during the specified time
interval. For example, setting the task frequency to Every 1 hour From
10:00:00 AM until 10:00:00 PM allows the task to be run 12 times from
10 AM to 10 PM during one day.
In the Effective... area, set the following settings:
From: <...> Set up a date when this schedule will be enabled (an effective date). If this
check box is cleared, the task will be started on the nearest day and time you
have specified above.
To: <...> Set up a date when this schedule will be disabled. If this check box is cleared,