Delta Pro S / Delta Pro Pack : 664Y4900 • E
Flue diameter type B23
Height
5 m 10 m 15 m
Delta Pro S 25
Ø mm 120 100 100
Delta Pro Pack 25
Delta Pro S 45
Ø mm 160 140 125
Delta Pro Pack 45
Delta Pro S 55 Ø mm 180 150 135
BOILER ROOM
- The flue connection must be carried out in compliance with the standards
in force, for example NBN D51-003, taking account of local energy supplier
and fire regulations as well as regulations relating to “noise pollution”.
- Make sure that all air vents are unobstructed.
- Do not store flammable products in the boiler room.
- Make sure that corrosive products, such as paint, solvents, chlorine, salt,
soap and other cleaning products, are not stored near to the boiler.
- The boiler must be placed on a non-combustible surface.
Accessibility
The boiler room must be large enough to allow good access to the boiler. The
following minimum distances are required around the boiler: (500 mm in
front, 200mm to the sides, 150mm behind and 700mm above).
OPTIONAL BALANCED FLUE
CONNECTION KIT (code : 10800264)
Available only for Delta Pro S & Pro Pack 25/45 models.
B23 FLUE CONNECTION
IMPORTANT:
The boiler is to be installed by a qualified engineer,
inaccordance with current regulations.
The diameter of the Flue must not be smaller thanthat of the
boilers flue reduction collar.
Boiler room ventilation
The boiler room must be fitted with top and bottom vents.
The tables below give the values defined according toBelgian
regulations.
Given that regulations vary from one country to thenext, these
tables are given for information only.
Each installer must ensure that boiler room ventilation
complies with current regulations.
INSTALLATION