Datasheet

2016 product data manual of PLANTOWER
Circuit Attentions
1) DC 5V power supply is needed because the FAN should be driven by 5V.
But the high level of data pin is 3.3V. Level conversion unit should be
used if the power of host MCU is 5V.
2) The SET and RESET pins are pulled up inside so they should not be
connected if without usage.
3) PIN7 and PIN8 should not be connected.
4) Stable data should be got at least 30 seconds after the sensor wakeup
from the sleep mode because of the fans performance.
Installation Attentions
1) Metal shell is connected to the GND so be careful not to let it shorted with
the other parts of circuit except GND.
2) The best way of install is making the plane of inset and outset closely to
the plane of the host. Or some shield should be placed between inset and
outset in order to prevent the air flow from inner loop.
3) The blowhole in the shell of the host should not be smaller than the inset.
4) The sensor should not be installed in the air flow way of the air cleaner or
should be shielded by some structure.
5) The sensor should be installed at least 20cm higher than the grand in
order to prevent it from blocking by the floc dust.
6) Do not break up the sensor.
7) M2 self-tapping strew should be used to fix the sensor but it should not be
deeper than 5mm into the sensor.
Other Attentions
1) Only the consistency of all the PM sensors of PLANTOWER is promised
and ensured. And the sensor should not be checked with any third party
equipment.
2) The sensor is usually used in the common indoor environment. So some
protection must be added if using in the conditions as followed:
a) The time of concentration 300μ g/m³ is longer than 50% of the
whole year or concentration500μ g/m³ is longer than20% of the
whole year.
b) Kitchen
c) Water mist condition such as bathroom or hot spring.
d) outdoor