User guide

© 2008 ATM FLY-WARE Signal Hill, CA 90755 USA (562) 424-1100
REV01 –Revised illustration and steps of installation-022510
LTMB24-X2-RK
Installation Instructions LT MB24 2 Wide Rigging Kit Grid
Thank you for choosing the LTMB24-X2-RK Grid. The LTMB24-
X2-RK Rigging Kit suspends two BOSE LTIII MB24 speakers in
2 wide arrangements.
Important:
Rigging overhead system requires professional experience.
Improperly installed equipment can result in property
damage, personal injury, death and/or liability to the
installing contractor. Do not suspend if in doubt about the
integrity of the structure.
Caution: Due to the wide variety of structures, environments,
materials and rigging methods, the installing contractor must
exercise good judgment in selecting the proper mounting area
and hardware.
Follow these instructions for the most efficient and safest
rigging results. Do not exceed the working load limit of
1000 lbs/455 Kg.
Package Contents:
2 pcs. LTMB24-X2-RK GRID
1 pc. Instruction sheet, 8.5X11
8 pcs Hex Cap, 3/8-16x1.5,G8, blk
8 pcs. Split washer, 3/8, G8, blk
8 pcs. Flat washer, 3/8”, SAE
4 pcs. Nyloc nuts, ½-13
Step 1:
Check to make sure the holes of the grid matches
the holes on top and bottom of the speaker.
Remove and discard speaker screws where the
grid will be attached
Step 2:
Set two speakers on the clean or padded floor with
the front facing the same direction. Lay the grid
over the top of the speakers and match the holes
to the holes on the speaker. Attach grid to
speakers using the supplied 3/8 hex bolt, washer
and split washers. Tighten bolts permanently
(Figure 1).
Step 3:
Attach load rated suspension cables to the
suspension bracket on the four corners of the grid
using load rated hardware such as shackles
(Figure 2). One can use four cable suspension
points or four points bridled to a two point
suspension.
Figure 1

Summary of content (2 pages)