User's Manual

Managing and Planning an LGCell Project
6-6 LGCell 4.0 Installation, Operation, and Reference Manual PN 8100-40
620004-0 Rev. B
Frequency Planning
Coordinate frequency planning with local carriers
Discuss with the local carrier the channel requirements for the system.
Final System Design
Complete final design
Generate a final design based on preliminary design, results of RF tests, discus-
sions with all appropriate parties involved in the project, and the site evaluation.
Create final equipment list
Generate a final equipment requirement list based on the final system design.
Design review
Discuss the final system design with all appropriate parties involved in the project.
RF Survey Report
Generate an RF Survey Report documenting all design information that you gath-
ered.
Traffic analysis of current requirements
Determine capabilities in terms of current and future capacity, coverage, and qual-
ity of service.