System Optimization and Commissioning
6.4 System Optimization and Commissioning
After the RF Site Survey is completed and the system is installed, perform the follow-
ing tasks.
Check Installation
Check installation of the Main Hubs, Expansion Hubs, Remote Access Units, split-
ters/combiners, antennas, etc.
Confirm all cable connections
Confirm working condition of LGCell equipment
Confirm that equipment quantities and equipment locations are documented
Confirm that all equipment and cables are identified and marked with ID number
Check Cabling
Review test results of Cat-5 cable (UTP/STP) (conduct cable test if testing has not
already been completed; the results are needed for the As-Built Document)
Review test results of coaxial cables; at base station to Main Hub and RAU to
antenna
Confirm and document actual link budget in coaxial cables
Check Optical Loss and Power Levels
Confirm and document downlink power level out of base station
Confirm and document downlink power level into Main Hub
Confirm and document uplink power level out of Main Hub
Check and document optical loss from Main Hub to Expansion Hub
Verify Coverage
Conduct floor-by-floor system walk-through, confirming RSSI in all locations of
the coverage area. Document RF signal level readings from all locations onto floor
plan drawings.
Confirm outside signal levels where required
Measure RF signal out of equipment, if required
Check Signal Quality
Check for neighbor channels/frequencies
Confirm adjacent channel/frequency signal strength
Check all call quality requirements of the carrier