User's Manual Part 3

Advanced RF Technologies, Inc.
97
8.2.4.2.1 RFU Commissioning
This section allows the user to perform RFU commission. To perform RFU commissioning, select a DL Input
Commissioning Level from the dropdown menu and click Apply. The commissioning progress is displayed on the
Commissioning Progress bar. Any errors, warnings, and messages will appear via a popup window. Please refer to
the ADX Installation Guide to determine the proper RFU commissioning levels.
Figure 8-70 RFU Commissioning (Install RFU)
8.2.4.2.2 Description
This section allows the user to set the description of RFU.
Figure 8-71 Description (Install RFU)
8.2.4.3 Install OPT
Figure 8-72 Install OPT
8.2.4.3.1 Optic Commissioning
This section will allow the user to perform any optic compensation if it is necessary. The Commissioning
button will turn orange if optic compensation is needed.