PROCEDURE
FOLLOW-UP PROCEDURES
All applicable modules, including SCU and the required M13 MUX modules, have been
installed. Follow-up procedures should be observed in accordance with CO SOP.
If STS-1 MUX modules are to be deployed, refer to “NTP-003, Clock Module Installation”.
Perform the Steps Below in the Order Listed: For details, refer to:
1. Install Modules in MX2820 Shelf:
Unpack, inspect, and install the primary M13 MUX Module.
Unpack, inspect, and install the protect M13 MUX Module, if required.
Install front panel blanks in vacant slots.
DLP-505
2. Provision the DS3/DS2 network. DLP-730
3. Provision the DSX-1 (T1/E1) interface. DLP-737
4. Provision M13 MUX protection. DLP-738
5. Provision M13 MUX loopback timeout. DLP-739
6. Perform acceptance testing for M13 MUX Modules. DLP-602