11. Locate the large flat bracket from the field kit. Place one end of the bracket over the bolt
on the bottom side of the lower right-hand hinge on the battery cabinet and the other end
over the bolt on the bottom side of the lower left-hand hinge on the UPS cabinet.
12. Secure the bracket to the hinges with hardware from the field kit.
13. Route the ground wire (from the field kit) from the ground stud in the battery cabinet,
under the lower right-hand battery tray, through the access hole in the side panel of the
UPS, and attach to the ground stud in the UPS cabinet. Hardware is provided on each
ground stud.
14. If installing additional battery cabinets, repeat Steps 2 through 13 to join each additional
battery cabinet; otherwise, proceed to Step 15.
Figure 13. UPStobatterycabinetattachingbrackets.
15. If not already installed, mount the hanger brackets to the top left side of the last battery
cabinet using M4 screws.
16. If not already installed, hang the side panel on the hanger brackets and align with the
front and rear of the battery cabinet.
17. If not already secured, secure the side panel at the bottom using M4 hex head screws
previously removed.