Item Connections
X1
Internal inverter bus and power supply
X2
Potential-free serial RS-232 interface
X3
Triggering of "Remote signalling"
X4
nn
X5
P
otential-free serial RS-485/RS-232 interface
J1
Configuration jumper, 1-2 firmware update, 2-3 (default)
J4
Configuration jumpers, all connected, RS-485 (default)
J5
Configuration jumpers, all connected, RS-232 (default)
S1
Button for initiating the configuration via connector X2
Table 14 - Interface assignment
The transmission topology of the Modbus interface (connector X5)
is set by means of the two configuration jumper blocks (J4/J5).
RS-485 is set at the factory.
In order to be able to use the Modbus interface as a point-to-point
connection via RS-232, you must remove all jumpers from block 4
and plug them in on block J5.
LED Signal
green/red flashing
Configuration can be selected via the terminal
(up to 30 seconds after restarting)
green on
Operating status; no external communication via
X2 and X5
green flashing
Data transmission to the serial interfaces X2 or
X5
red on
Fault
Table 15 - LED signalling
7.7.1 Description of Interfaces
Port 1: Serial interface X2, RS-232 pin assignment
The potential-free serial RS-232 interface at connector X2 is de-
signed for parameterising the interfaces on the MCC via a terminal
program, and for special service tools.
A 1:1 data cable is required.