The opening lever for the LV main distributor is accessible when
the door to the inverter is open.
Insert the AC power connections from below and screw them to
the cable lug using the relevant tightening torque.
1 2 3 4 5 6 1 2 3 4
Figure 13 - PV.630-MH low-voltage connections
1 Connection L1 - X26:U
2 Connection L2 - X26:V
3 Connection L3 - X26:W
4 Connection - X26:PE
5 Load interrupter switch Q26.n
6 Protective cover (Makrolon)
i
The order of the conductors (L1, L2, L3) must be adhered to.
Establish AC power connections and PE connections in the
compact station in accordance with the circuit diagram and using
the relevant tightening torque.
Remove any cable debris and tools from the equipment and
replace the protective cover on the connection panel.