8 Start-up
DANGER
Working with voltages up to 1 kV
Risk to life due to electric shock.
Comply with BGV A3, DIN VDE 0105-100
(EN 50110, IEC 61243).
Skilled personnel with a Working with Live Current
certificate.
i
The electrical equipment must not be started up/operated if
there are any traces of condensation.
Starting up the Protect PV.xxx-MH correctly for the first time
assumes that all the components in the solar power station have
been correctly installed, wired and earthed. When starting up for
the first time, the equipment owner must obtain authorisation to
work with switchgear for the purposes of connecting the transfer
station, and must tell the local grid operator when the connection
will occur.
Instructions: Requirements for Start-Up
of AEG PV Inverter(s)/Station(s).
Instructions: Requirements for Start-Up
of PV Powerplant Monitoring.
Equipment information for start-up from Skytron
Once the requirements have been fulfilled and all assembler
certificates and test reports for the PV power station are present,
the person carrying out the initial start-up checks that they are
complete and accurate. For legal reasons, this person is obligated
to check all components and values again in accordance with the
start-up log, and to document the results.
Special AEG PS software and hardware tools are required for
initial start-up; therefore, it is recommended that AEG PS service
personnel carry out the initial start-up process.
Skilled personnel working for the equipment owner are only in a
position to use these tools correctly and to perform initial start-up
correctly once they have been trained in this area.
Further information regarding start-up can be found in Installation and Start-up
(BAL) Protect PV.500 or operating instructions PV.6x0/8x0-ID
9 Operation
All information regarding operation can be found in the Operating Instructions
Protect PV.500 or PV.6x0/8x0-ID.