Instruction Manual

Benchmark 750/1000 Boiler Installation, Operation & Maintenance Manual
CHAPTER 3 OPERATION
Page 50 of 192 AERCO International, Inc. 100 Oritani Dr. Blauvelt, NY 10913 OMM-0082_0J
05/21/2014 Ph.: 800-526-0288 GF-130
Menu Item Display
Available Choices or Limits
Default
Minimum
Maximum
Comm Address
0
127
0
BST Min Addr
1
128
1
BST Max Addr
1
128
8
SSD Address
0
250
247
SSD Poll Control
0
1000
0
Err Threshold
1
9
5
SSD Temp Format
Degrees
Points
Degrees
BST Upld Timer
0
9999 sec
0
3.10 START SEQUENCE
When the Control Box ON/OFF switch is set to the ON position, it checks all pre-purge safety
switches to ensure they are closed. These switches include:
Safety Shut-Off Valve (SSOV) Proof of Closure (POC) switch
Low Water Level switch
High Water Temperature switch
High Gas Pressure switch
Low Gas Pressure switch
Blower Proof switch
Blocked Inlet switch
If all of the above switches are closed, the READY light above the ON/OFF switch will light and
the unit will be in the Standby mode.
When there is a demand for heat, the following events will occur:
NOTE
If any of the Pre-Purge safety device switches are open, the
appropriate fault message will be displayed. Also, the appropriate
messages will be displayed throughout the start sequence, if the
required conditions are not observed.
1. The DEMAND LED status indicator will light.
2. The unit checks to ensure that the Proof of Closure (POC) switch in the downstream
Safety Shut-Off Valve (SSOV) is closed. See Figure 3-3 for SSOV location.