User`s guide

Chapter 1 1-89
System Verification and Performance Tests
Performance Tests
7. Press REFLECTION, FORWARD:OPEN, OPEN (F), DONE OPENS.
8. Connect the short to Port 2.
9. Press FORWARD: SHORT, SHORT (F) DONE SHORTS.
10.Replace the short with the 50 termination (supplied in the
calibration kit).
11.Press FORWARD:LOAD.
12.Connect the open to reference test port 3.
13.Press REVERSE:OPEN, OPEN (M), DONE OPENS.
14.Connect the short to reference test port 3.
15.Press REVERSE: SHORT, SHORT (M), DONE SHORTS.
16.Connect the 50 termination to reference test port 3.
17. Press REVERSE: LOAD.
18.When the analyzer displays PRESS ‘DONE’ IF FINISHED WITH
STD(s), press STANDARDS DONE.
Wait for the message COMPUTING CAL COEFFICIENTS to disappear
from the analyzer’s display before proceeding to the next step.
19.Connect the equipment as shown in Figure 1-43.
Figure 1-43 Transmission Calibration Test Setup (Port 2 to Port 3)
20. Press TRANSMISSION, DO BOTH FWD + REV.
21. Press DONE 2-PORT CAL.