Sequence Commands
The test set I/O may be set using the test sequencing function.
Sequence Example
The following example sets up the port configuration for Port 1 to Port 2,
and for Port 2 to Port 3:
1. Press Seq, NEW SEQ/MODIFY SEQ, SEQUENCE 1, SEQ1, TTL I/O, TTL OUT.
2. Press TESTSET I/O FWD, 5, x1.
3. Press TESTSET I/O REV, 5, x1, Chan 1.
4. Press RETURN, RETURN, DONE SEQ MODIFY.
5. Press MORE, TITLE SEQUENCE, SEQUENCE 1, SEQ 1, ERASE TITLE.
6. Rotate the front panel knob and select the following:
P, SELECT LETTER, 1, SELECT LETTER, 2, SELECT LETTER, DONE,
RETURN
.
7. Press NEW SEQ/MODIFY SEQ, SEQUENCE 2, SEQ1, TTL I/O, TTL OUT.
8. Press TESTSET I/O FWD, 6, x1.
9. Press TESTSET I/O REV, 6, x1, Chan 1.
10.Press RETURN, RETURN, DONE SEQ MODIFY.
11.Press MORE, TITLE SEQUENCE, SEQUENCE 2, SEQ2, ERASE TITLE.
12.Rotate the front panel knob and select the following:
P, SELECT LETTER, 2, SELECT LETTER, 3, SELECT LETTER, DONE,
RETURN
.
13.Press Preset.
The softkeys on the display should show SEQUENCE 1 P12,
SEQUENCE 2 P23
. For more information about sequencing and its
capabilities, refer to the standard documentation.
Pressing SEQUENCE 1 P12 sets the analyzer to measure between Port 1
and Port 2.
Pressing SEQUENCE 2 P23 sets the analyzer to measure between Port 2
and Port 3.