User`s guide
Chapter 1 1-17
System Verification and Performance Tests
System Verification
8. When the analyzer finishes all the measurements, connect the
mismatch verification device as shown in Figure 1-7. Notice that
Port B is now connected to reference test port 1.
Figure 1-7 Mismatch Device Verification Setup 2
9. Press RETURN, TESTS, 31, x1, EXECUTE TEST, CONTINUE.
10.You have completed the system verification procedure when the
analyzer displays Ver Def 4 DONE.
Port 2 Verification
Perform the Port 2 verification to ensure the proper operation of the
analyzer. Port 2 verification consists of doing all the Port 2 to Port 3 and
Port 1 to Port 2 verification tests in “9. Uncorrected Port Performance” on
page 1-80, found in the performance test records.