Specifications

Fully Coded 3GPP W-CDMA Personality Users and Programming Guide 2-109
ESG Family Signal Generators Using Functions
Option 200 3GPP W-CDMA Base Station Performance Testing
Example Test Procedure
Follow this example procedure to perform a 3GPP W-CDMA intermodulation response
rejection test on your BS. Perform the subsections in this procedure sequentially, in the
order they appear in this document.
Subsection 1. Equipment Setup and Preliminary BER Verification
Complete the following steps to connect the equipment and perform a BER verification test
on your BS.
Figure 2-20 Intermodulation Response Rejection Equipment Setup
1. Connect the BS to the test system as shown in Figure 2-20.
a. Using the appropriate cables, adapters, and antennae, connect the outputs of the two
ESGs and one RF signal generator to the RF input ports of the signal combiner.
b. Connect the RF output port of the signal combiner to the RF input of the BS.
c. Connect the system controller and the BER test platform to the BS.