User Manual

AS4000 Access Concentrator
Installation and Commissioning
DLP 001
605-0000-453
Issue 1.2dr Date 7/02/00
Page 2 of 4
1.2. Required Equipment
Item Description Recommended Model Quantity
1 Digital Multimeter Fluke 77 or similar 1
2
3
4
5
6
7
Table 4. Required Test Equipment.
2. Site Readiness
Verify that the site is ready for the installation of the AC Rack.
This preparation will have been covered by a site survey conducted by ACC or by a
survey form completed by the customer. The survey will include a site plan of the
facility identifying the floor layout, power outlets, distribution boxes, and cabling
runways. A sketch showing the rack support arrangements showing the exact
positions of the mounting points on the rack with dimensions, and typical overhead
ironwork provision should be included.
Inspect the site, and particularly the equipment room, before unloading or unpacking
the equipment to ensure the following:
Adequate grounding is provided.
Access to the equipment room will be adequate for normal handling and movement.
Adequate lighting is available for carrying out the installation.
Any non compliance with acceptable standards should be bought to the customers
attention and resolved before proceeding with the installation.
2.1. Power Availability
From the site survey, confirm the location of the two fuse positions for the negative
battery supply and the return point. Also locate the fuse position for the alarm unit 55B
power supply.