1. Positioning and Securing
1.1. In a Suite
From the site survey, confirm the position of the CT Rack. If the rack is to be
positioned in a suite, metalwork will be required to secure it to the overhead
structure. Either a proprietary system or fabricated steelwork will be required -
see site survey.
Manoeuvre the rack into position.
2.2 m
600 mm
300 mm
DSC
Modem Shelf 1
Modem Shelf 2
Modem Shelf 3
Modem Shelf 4
RF
Combiner
Shelf
Figure 2. Central Terminal Rack.
Using the base of the rack as a template, mark the floor locating positions
through the welded nuts in the Rack Frame. Using a 13mm. diameter drill bit,
drill four holes to a depth of approximately 25mm. Position the CT rack over
the four holes and screw the four (supplied) M12 screws through the rack base.
Warning: These screws are provided as locating pins only and must be
used in conjunction with the overhead steelwork and not as an alternative
method for securing the rack.
Temporarily secure the rack to adjacent racks or steelwork until the overhead