_____________________________________________________________________________
AirWalk Proprietary and Confidential Page 38 of 54
4) Determine when contacts are available for help (e.g.; Time of day, day of week.) for
customer, installation teams and persons involved in the site planning.
5) Obtain any site access or security requirements (e.g.: ID Badges, Card-keys, Keys,
Access codes) required to access installation site.
6) Locate the AirWalk IP-RAN equipment and any required support equipment.
Arrange transportation of equipment to the site, if required.
7) Check for any visible shipment damage to the equipment prior to transportation or
installation. If any damage is observed, then notify the carrier or responsible party
to resolve any insurance inspection issues prior to handling or opening the
packages.
7.1.2 Locate and verify floor space
1) Determine where the IP-RAN equipment is to be installed. Obtain and review site
documentation including diagrams, floor plans and connection requirements before
visiting the site.
2) Visit the site and verify that there is enough space to safely install the AirWalk units
(refer to Site Preparation Checklist in Appendix B).
7.1.3 Uncrate and arrange for packing material disposal2
1) Carefully unpack the AW-100 and related components from packing material.
2) Check for any shipment damage.
3
3) Be certain that all components match system order.
4
4) Make arrangements for the disposal of all packing material discarded during
installation.
Some crating materials may require return to the manufacturer or warehouse for reuse
and therefore suitable arrangements must be made.
7.1.4 Verify location of power distribution points
1) Locate the customer or site provided power connection points and verify adequacy.
2) AC powered models require a designated 120 VAC minimum 15A or 240 VAC
minimum 7A outlet. No other equipment or receptacles should be connected to this
outlet, other than low power accessories needed to support the IP-RAN operation
such as an Ethernet switch. Use only the 6’ power cord supplied with the IP-RAN
unit.
2
NOTE: If any visible damage, contact the Installation Coordinator immediately.
3
NOTE: Note any damage on the receivables receipt, and Installation Checklist. Contact
the Installation Coordinator immediately.
4
NOTE: If components do not match the system order, contact the Coordinator
immediately.