Figure 7-6 IP-RAN Configuration Screen (“running mode”)
Configuration changes are entered using this screen and accepted by the IP-RAN by
clicking on the “Submit” button. However, the new changes will NOT become effective
until the IP-RAN unit is rebooted. This can be done by clicking on the “Reboot” button.
Once the IP-RAN unit reboots, it will use the new configuration information to contact the
controlling iBSM system to download software images and/or configurations, as required
or defined in the “bootoptions” setting.
7.3.5 Additional Operation Tests
Additional operational tests may be required by the RF system/planning engineer, the
network control centre engineers, or others in order to complete the base site installation.
Such tests could include:
- Power output measurement (PPS or PN3383)
- Alarm function testing
- Test calls using mobile handsets or data terminals
- Drive testing and RF coverage/performance measurement
Refer to the individual test checklists for completion and recording of any additional
installation test activities.
7.4 Site Cleanup and Customer Signoff
The following activities must be undertaken prior to completion of the site installation:
- Disposal of all packing and installation materials, including wire clippings
- Replace all equipment, covers, doors and other site equipment