Step 3. Verify that the opening is plumb and that the floor slab is level. If they are not, shimming and
adjustments to the side frames must be made to accomplish this during door installation. Refer to
approval drawings for this door to confirm drive side mounting (left or right-hand).
Step 4. Remove side frames from crate (one at a time) and erect them into position against the wall at the
pre-marked locations on the floor.
Step 5. Plumb the side frames and temporarily secure them to the wall using C-clamps. (Figure 2)
Step 6. Using an approved lifting device, place a lifting
strap around the top roll assembly, lift and remove from
shipping crate as indicated by Figure 3. Slide the operator
onto the stub axle, Figure and attach to the top roll
assembly with the supplied hardware. Or it can be added
after the top roll assembly is bolted to the side frames
Raise the top roll assembly into position and lower it
slowly onto the top of both side frames. Using
supplied 3/8” –16 bolts, fasten the side frame top plates to
axle bearing plates using the three-corner bolt holes
(Figure 4).
NOTE
POSITION THE LIFTING DEVICE AND STRAPS
ACCORDINGLY AS THE DOOR WILL BE HEAVIER
ON THE DRIVE SIDE IF YOU ATTACHED THE
DRIVE BEFORE LIFTING INTO PLACE. DO NOT
REMOVE THE LIFTING DEVICE UNTIL THE
DOOR IS PERMANENTLY
ATTACHED TO WALL.
NOTE
THE NEXT STEP INVOLVES INSTALLING THE TOP
PULLEY BRACKETS. PRIOR TO DOING SO,
ENSURE THE DRIVE UNIT IS ATTACHED
(Figures 5A and 5B) AND THE BRAKE IS NOT
RELEASED.
Step 7. In order to allow clearance for installing the top
pulley brackets, the door fabric must be lowered a
maximum of two feet. Tie a rope around the top
roll, leaving approximately two feet of slack
(Figure 5)
FIGURE 2