A.1.4 – LIST OF CHECKPOINTS FOR TS COMMISSIONING
CHECK SAFETY RULE
Equipment grounding OK NOK
Differential protection OK NOK
Fire protection OK NOK
CHECK RT INSTALLATION
No pollutants or possible flow on the X-Pol RT OK NOK
No possible trespassing in the X-Pol RT antenna field OK NOK
Direct view between X-Pol RT antenna and base station antenna OK NOK
Use of a torque wrench for the X-Pol RT assembly OK NOK
Support stiffness and absence of vibrations OK NOK
Same polarization as for base station antenna OK NOK
CHECK CABLES BETWEEN X-Pol RT and NT
–F 75 connectors X-Pol RT side OK NOK
Watertightness by thermoshrinkable pre-pasted sleeve X-Pol RT side OK NOK
No cable strain OK NOK
Observe minimum bend radius OK NOK
CHECK NT INSTALLATION
Min Max temperature of the premises hosting the NT (-5º to + 55ºC) OK NOK
Ventilation clearance above the NT OK NOK
Check the NT grounding OK NOK
Check that all client access cables are shielded cables OK NOK
Diagram compliant with multi-NT connection OK NOK