User's Manual

Site requirements
General requirements
The following general requirements must be met before the installation of the 9927
Distributed Base Station site can be started:
An appropriate installation site must be selected. For more information, see
“Mounting options” (p. 5-9).
Adequate clearance
must be provided for service access, as described in “Support
structure” (p.
5-11).
The environment
must comply with “Environmental requirements for outdoor
installations” (p.
5-4).
Cabinet anchor
holes must be drilled, as described in “Drill anchor holes” (p. 5-16).
Support structure
and ice bridge (if required) must be installed, as described in
“Support structure, ice bridge and service access clearances” (p. 5-11).sss
Tower
light power must be installed (if required).
Tower light alarm must be installed (if required).
Conduits must be installed, as described in “Conduit requirements” (p. 5-7).
AC electric
service for the 9927 Distributed Base Station Outdoor Cabinet must be
installed as described in Chapter 8, “Electrical power requirements for 9927
Distributed Base
Station Outdoor Cabinet”.
DC electric
service for the RRHs must be installed as described in Chapter 8,
“Electrical power
requirements for 9927 Distributed Base Station Outdoor Cabinet”.
GPS antenna
runs must be installed, as described in Chapter 10, “Site preparation
requirements for
9927 Distributed Base Station Outdoor cabinet GPS antenna and
microwave antenna cable”.
Sur
ge
protection for antennas must be installed, as described in Chapter 10, “Site
preparation requirements
for 9927 Distributed Base Station Outdoor cabinet GPS
antenna and microwave antenna cable”
Grounding
electrode
system must be installed with sufficient pigtails, as described in
Chapter 12, “Grounding and lightning protection requirements for 9927 Distributed
Base Station
Outdoor Cabinet”.
T1/E1 and
User Alarm facilities must be installed at demarcation point as described in
Chapter 14, “Site preparation -- T1/E1 and User Alarm facilities for 9927 Distributed
Base Station
Outdoor Cabinet”.
Refer to Appendix
A, “9927 Distributed Base Station Outdoor Cabinet site preparation
checklists” of this document for checklists of detailed requirements.
Basic site preparation requirements and footprints for 9927
Distributed Base Station outdoor cabinet
Site requirements for 9927 Distributed Base Station
Outdoor cabinet
Site requirements
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
5-6