User's Manual

1-4
Lucent Technologies – Proprietary
See notice on first page
401-703-454
FOA Draft Issue 1
January, 2006
...........................................................................................................................................................................................................................................................
Overview of the Flexent‚ Modular Cell 4.0B cabinet
installation
Site preparation
Before installation of the Modular Cell 4.0B cabinet can begin, site
preparation should have been completed.
Refer to Flexent Modular Cell 4.0/4.0B Outdoor Site Preparation
Guidelines, 401-703-413.
The following requirements must be met at the installation site, prior to
installation of the Modular Cell 4.0B cabinet:
Adequate clearance must be provided for service access.
The environment must comply with the specifications set forth in
the site preparation guidelines.
AC electric service must be installed as described in Chapter 5 of
the site preparation guidelines.
T1/E1 facilities must be installed at demarcation point as
described in Chapter 8 of the site preparation guidelines.
Balun Protector Box must be installed, if required.
User alarm must be installed at demarcation point.
Grounding system must be installed.
RF and GPS antenna runs must be installed.
Surge protection for antennas must be installed.
Cable support must be installed.
Tower light power must be installed (if required).
Tower light alarm must be installed (if required).
Cabinet support structure must be in place.
Ice shield must be installed, if required.
Cabinet anchor holes must be drilled.
Mounting base must be installed, if required.
Product specification -
outdoor installation details
Outdoor cabinets may be installed in either controlled or uncontrolled
environments. This equipment has been evaluated for use in an ambient
temperature range from -40 to 52° Celsius.
The cabinet must only be mounted on a concrete pad or other
noncombustible surface.