Cable connections in the Modular Cell 4.0B cabinets
How to route the T1/E1 cable(s) to a Modular Cell 4.0B dual band
cabinet in a line-up that has a Modular Cell 3.0, 4.0, or 4.0B primary
.............................................................................................................................................................................................................................................................
cabinet with integrated power
Important! If installing a Modular Cell 4.0B dual band cabinet
in a line up that has a 1.0, 2.0, 3.0, 4.0 or 4.0B primary cabinet
without integrated power, skip to How to route the T1/E1 cable(s) to
a Modular Cell 4.0B dual band cabinet in a line-up that has a Modular
Cell 1.0, 2.0, 3.0, 4.0, or 4.0B primary cabinet without integrated power
on Page 3 - 18 and continue the installation from that point.
Important! This procedure module provides instructions for the
routing of the T1/E1 cable(s) to a Modular Cell 4.0B dual band
cabinet, that has been installed with a line-up that has an existing
3.0, 4.0, or 4.0B Modular Cell primary cabinet with integrated
power.
Route T1/E1 cables to the
Modular Cell 4.0B dual
band cabinet
Important! The number T1/E1 cables to be routed will vary
depending upon the Universal Radio Controller (URC or URCII)
in use in the 4.0B dual band cabinet being installed. A URC
accepts a maximum of twelve TI/E1 lines, and requires only one
cable. A URCII accepts a maximum of twenty TI/E1 lines, which
requires an additional cable.
Perform the following steps to route the T1/E1 cables to the Modular
Cell 4.0B dual band cabinet.
Important! If the existing primary cabinet has a 66ECv2
battery cabinet attached (which utilizes a vertical duct for cable
routing) do not route the T1/E1 cables through the vertical duct
unless the antenna cable cover conduit is not present
.....
......................................................................................................................................
1 Locate the T1/E1 cables and pull them through the existing conduit and
into the antenna cable cover of the primary cabinet. Refer to the figure
on Page 3-17.
................................................................................................................................
............................................
2 Using a #8 drilled spanner driver, remove the applicable rear panels
from the antenna cable covers of the Modular Cell cabinets. Refer to the
figure on Page 3-17.