Component installation in the Modular Cell 4.0B and the
WNG24-BC battery cabinets
5- 89
Lucent Technologies – Proprietary
See notice on first page
401-703-454
FOA Draft Issue 1
January, 2006
............................................................................................................................................................................................................................................................
................................................................................................................................
............................................
1 At the first battery cabinet, measure the voltage at the connector of each
of the newly installed battery cables, to determine if the polarity is
correct. Use the procedure provided on Page 5 - 9, Step 11. Refer to the
figure on Page 5-90, item 1.
................................................................................................................................
............................................
2 Repeat the test in the previous step, for the battery connectors to be
plugged into the ones already tested.
................................................................................................................................
............................................
3 Rewire any battery cables found to be incorrectly wired.
Important! If installing the first battery cabinet only, skip the
next two steps.
................................................................................................................................
............................................
4 Repeat Steps 1 and 2 for the second battery cabinet.
................................................................................................................................
............................................
5 Rewire any battery cables found to be incorrectly wired.
Important! Before performing the next step, be sure that AC
power is connected to the Modular Cell 4.0B cabinet, AC power is
turned on at the main panel, and all AC circuit breakers are ON at
the primary cabinet.