January, 2006
...........................................................................................................................................................................................................................................................
Finishing the installation
.............................................................................................................................................................................................................................................................
Power-up and system test
Perform power-up and
system test
Following installation of the Modular Cell 4.0B primary or dual band
cabinets, the system should be tested before being put into operation.
System test and integration procedures are not covered in this
installation document. This information is contained in Lucent
Technologies Installation Engineering Handbook 238. Consult the
specific reference below. Power-up and system test can be performed if
the following tasks are completed.
All cabinets are installed as specified in this document.
The GPS antenna cable is connected.
RF antenna jumper cables are not connected to the Modular Cell
4.0B primary or 4.0B dual band cabinets.
Important! Refer to Lucent Technologies Installation
Engineering Handbook 238 for procedures for power-up and
stand-alone testing. Section 221 is for power-up.