User's Manual

Modular Cell 4.0B and WNG24-BC cabinet handling,
placement, anchoring and grounding
2- 5
Lucent Technologies – Proprietary
See notice on first page
401-703-454
FOA Draft Issue 1
January, 2006
............................................................................................................................................................................................................................................................
.............................................................................................................................................................................................................................................................
Anchor installation
Mark and drill the anchor
holes
Important! Note that outdoor cabinets may be mounted directly
on a concrete or on optional steel mounting bases. EZBFo battery
frames may be mounted directly on a concrete pad. Procedures for
the preparation of other types of mounting surfaces are the
responsibility of the customer.
If not already accomplished during site preparation, use the following
procedure to mark and drill the anchor holes in a concrete surface.
.....
......................................................................................................................................
1 Mark the surface for all cabinets to be installed (using the information
provided in the document listed below) for cabinet anchoring
dimensions, or steel mounting base anchoring dimensions.
Flexent
Modular Cell 4.0/4.0B Site Preparation
Guidelines, 401-703-413.
................................................................................................................................
............................................
2 If installing a EZBFo battery base module, consult the above document
and skip to Appendix A to continue the installation.
................................................................................................................................
............................................
3 Drill the anchor holes to the proper size and depth as specified in the
previous table. Refer to the figure on Page 2-6 for the anchor hole
drilling method.
Important! If a 4-inch hole depth cannot be attained for a 12-
mm expansion stud anchor (seismic zones 3 and 4), a spacer may
be removed from the anchor assembly, prior to the anchor being
set. In this case, 1 inch must be cut from the end of the threaded
rod, prior to the anchor being set. Refer to the instructions
provided with the anchor setting procedure.
................................................................................................................................
............................................
4 Vacuum out the holes. Refer to the figure on Page 2-6.