Modular Cell 4.0B and WNG24-BC cabinet handling,
placement, anchoring and grounding
Placement and anchoring of a Flexent Modular Cell 4.0B dual band
.............................................................................................................................................................................................................................................................
cabinet
Overview
This section provides the following instructions. The instructions
assume that the primary cabinet, regardless of model, 1.0/2.0/3.0/4.0,
or 4.0B, is already in place, and that if the primary cabinet is not a 4.0B,
that Legacy first and second growth may already be in place.
1. Placement, anchoring and grounding of an outdoor Flexent
Modular Cell 4.0B dual band cabinet in the G-1 position with a
4.0B primary cabinet
2. Placement, anchoring and grounding of a Flexent Modular Cell
4.0B dual band cabinet in the G-2 or G-3 position with Legacy
previous cabinets.
For purposes of these instructions the cabinet to which the 4.0B
dual band cabinet is to be attached will be referred to as the
previous cabinet, regardless of model or position in the existing
line-up.
Step-by-step instructions are provided for the following tasks.
Prepare the previous Modular Cell cabinet for connection of a
4.0B dual band cabinet
2 - 51
Partially install the AC cable guide in the previous Modular Cell
cabinet, if applicable
2 - 53
Prepare the 4.0B dual band cabinet for connection to the
previous Modular Cell cabinet
2 - 54
Position the 4.0B dual band Modular Cell cabinet 2 - 56
Install anchoring bolts or anchor assemblies and level the 4.0B
dual band cabinet
2 - 58
Finish the installation of the AC cable guide and tighten the
anchor bolts
2 - 60
Attach the 4.0B dual band Modular Cell cabinet to the previous
Modular Cell cabinet at the RF cable guide
2 - 62