If the LNK LED for the fiber optic port is ON, but there is a communication 
problem between the end-nodes connected to the media converter (and you are 
not running a Fiber Link Test), check the following:
q Check that the end-nodes connected to the ports are operating at 10 
Mbps.
q Check that the end-nodes connected to the AT-MC13, AT-MC14, or 
AT-MC16 are operating in the same duplex mode. These units can 
operate in either full- or half-duplex mode.
q Check that the Fiber Link Test switch on the media converter is in the 
DOWN position.
q Check that the maximum allowable loss budget for the fiber optic 
cable has not been exceeded. Refer to Table 7 on page 14 for the fiber 
optic port specifications.
If the NML LED on the AT-MC13, AT-MC14, or AT-MC16 is OFF, do the 
following:
q Check that the end-nodes connected to the media converter are 
powered ON.
q Check that the fiber optic cable is securely connected to the fiber optic 
port.
q Verify that the appropriate fiber optic cable is being used. Refer to 
Table 7 on page 14 and Table 8 on page 15 for the fiber optic cable 
specifications.
q Verify that the maximum allowable loss budget for the fiber optic 
cable has not been exceeded.
If you are still experiencing problems after troubleshooting the installation, 
contact Allied Telesyn Technical Support for assistance. Refer to “Contacting 
Allied Telesyn Technical Support” on page viii or visit our web site at 
www.alliedtelesyn.com for support information.