Te25xh Outdoor Power Enclosure 029-006-B2
This page intentionally left blank. Argus Technologies Ltd. Burnaby, British Columbia. Telephone: 604 436 5900 Fax: 604 436 1233 Argus Technologies reserves the right to make changes to the products and information contained in this document without notice. Copyright 2008 Argus Technologies Ltd. Argus® is a registered trademark of Argus Technologies Ltd. All Rights Reserved. Printed in Canada. Visit www.argus.
Te25xh Outdoor Power Enclosure 029-006-B2 The following documents and drawings are included in this manual to provide the necessary information required for routine installation of the enclosure.
This page intentionally left blank.
Specifications for Argus’ Te25xh Outdoor Power Enclosure Mechanical Dimensions (minimum): 914mm H x 544mm W x 518mm D; see outline drawings, (36" H x 21.4" W x 20.4" D) [dimensions vary depending on mounting and other options ordered] Mounting: Ground/pedestal or pole Weight (no batteries/rectifiers): 45.6 kg (100.5 lb.), no riser 55.1 kg (121.5 lb.), with riser 52.9 kg (116.6 lb.
Specifications for Argus’ Te25xh Outdoor Power Enclosure Continued Ordering Guide This product is available to order under the following part numbers and list options: Description Part Number/List Option Te25xh Outdoor Power Enclosure.............................................................................................................029-006-20 Standard unit c/w ground bar, 7” DIN rail, wind latch, intrusion alarm switch.................................................... *List 0 Quartz gray color..
IMPORTANT SAFETY INSTRUCTIONS SAVE THESE INSTRUCTIONS This manual contains important instructions that should be followed during the installation and maintenance of equipment and batteries. Please read all of the instructions before operating the equipment, and save this manual for future reference. A licensed electrician MUST perform connections to the branch circuit of service feed.
Electrical Safety WARNING Hazardous voltages are present at the input of a power system. The DC output from rectifiers and batteries, though not dangerous in voltage, has a high short-circuit current capacity that may cause severe burns and electrical arcing. Before working with any live battery or power system/distribution center, follow these precautions: • • • Remove all metallic jewelry; e.g., watches, rings, metal rimmed glasses, necklaces.
TABLE OF CONTENTS SECTION 1 INTRODUCTION ............................................................................................................................................................. 1 1.1 1.2 2 Ventilation ..................................................................................................................................................... 2 Security .............................................................................................................................
11 ARGUS CONVENTIONS ................................................................................................................................................ 15 11.1 11.2 Numbering System...................................................................................................................................... 15 Acronyms and Definitions ...........................................................................................................................
1 Introduction 1.1 Scope of the Manual This instruction manual explains the features, installation, and maintenance of Argus Technologies’ Tempest Te25xh Outdoor Power Enclosure. NOTE: Images contained in this document are for illustrative purposes only and may not exactly match your installation. Enclosure specifications may be found in Argus document #029-006-B1. Separate instructions will be provided with the batteries as ordered. 1.
2 Enclosure Features (Photo is for reference only – subject to installation requirements) Cooling fan assembly DIN rail Telco connections (4) Intrusion alarm switch Fan control thermostat Battery string disconnect Figure 2–Te25xh with front door open showing internal features 2.1 Ventilation The Te25xh Compact Power Node enclosure is designed with louvers and a thermostat-controlled fan assembly (shown above) providing filtered ambient air-cooling to the equipment within the enclosure.
GFCI outlet Master ground bar Figure 3–Inside upper front right (may not be exactly as shown) Cable knockouts are provided for access through rear and bottom panels. Refer to outline drawings at the rear of this manual. 2.4 Battery Tray A single battery tray is included with the Te25xh Compact Power Node for installing various battery models such as Alpha Technologies 85-GXL or similar. The tray dimensions are 470mm D x 432mm W (18.5” D x 17” W).
3 Transportation and Storage 3.1 Packaging The enclosure and components are shipped on individual pallets and shrink wrapped. The pallet is approximately 0.13m H x 1.07m W x 1.07m D (5” H x 42” W x 42” D) and the overall height including pallet and enclosure is approximately 1.1m (43”). The enclosures and components cannot be stacked. NOTE: Packaging assemblies and methods are tested to International Safe Transit Association standards. WARNING Never transport the unit with batteries installed.
4 Site Considerations The information in this section is intended as a guideline only; there may be site-specific requirements and other factors that will require individual attention, such as jurisdictional codes and construction covenants. 4.1 Site Selection The supporting structure must be designed to support a fully configured enclosure. This will require a concrete slab and any existing structures to be properly reinforced to support the floor loading.
5 Tools Required Various insulated tools are essential for enclosure and DC power system installation. Use this list as a guide: • • • • • • • • • • Battery lifting apparatus (as required) Various crimping tools and dies, to match lugs used in installation Digital voltmeter equipped with test leads Cable cutters Torque wrench: 1/4” drive, 0-150 in/lbs Torque wrench: 3/8” drive, 0-100 ft/lbs Insulating canvases as required (2’ x 2’, 1’ x 1’, 3’ x 3’, etc.
6 Enclosure Installation 6.1 Pedestal Mount Kit with Concrete Mounting Frame This kit is comprised of two kits: 037-146-20 (Brown Kit) and 037-182-20. See drawings 037-146-04 and 037-18204 at the rear of this manual. 1. Unwrap the enclosure and inspect the contents. If items are missing or damaged, contact Argus Technologies and the shipper immediately. 2. Unbolt the enclosure from the shipping pallet. 3.
7 Wiring and Connections This section is provided for qualified personnel to install and interconnect the power components within the Te25xh. Regarding battery installation, refer primarily to the manufacturer’s guidelines for more specific information. 7.1 Grounding DANGER An enclosure that is not properly grounded can present an electrical hazard.
7.2 AC Input Power Verify electrical codes prior to installation. Codes may vary and contain specific conduit and wire sizes for AC input power connections. Connection to utility power must be approved by the local utility before installing the power supply. 7.2.1 AC Load Centre (Example 1) This sample system is configured with a 100A 8-position load centre and a 70A 2-pole main disconnect equipped with a 30A breaker. Figure 7–Side view of example 1 NOTE: See schematic at the rear of this manual. 1.
7.2.2 AC Load Centre (Example 2) This sample system is configured with a 100A 8-position load centre and a 100A combination meter socket with provision for 2-pole main breaker (comes equipped with a 30A breaker). Figure 9–Side view of example 2 L1 L2 N NOTE: See schematic at the rear of this manual. 1. Locate the combination meter socket on the side of the enclosure and remove the front cover panel(s) to access the meter socket and circuit breaker interior assembly. 2.
7.3 DC Power Connections DC power connections include customer load/equipment circuit breakers and battery circuit breakers (pre-wired). Circuit breakers are labeled on the front panel of the DC distribution section of the rectifier shelf and each corresponding output power load cable set connection is marked on terminal block of system input/output termination panel. 7.4 Alarm Connections Alarm output connections are provided on system I/O termination panel.
8 Battery Installation WARNING Follow battery manufacturer’s safety recommendations when working around battery systems and review the safety instructions provided in this manual. 8.1 Preparation/Mounting The enclosure must be mounted before installation of the batteries may be completed. Batteries should be located in a temperature-controlled environment; i.e., Tempest. The temperature should be regulated at approx. 25°C (77°F).
9 Test Results 9.1 Acoustical Noise Test Condition: The equipment under test (EUT) was set up in a room with an acoustical background of 37.5dBA. 45.0dBA @ 1.5 m (4.9 ft) REAR RIGHT 42.0dBA @ 1.5 m (4.9 ft) EUT LEFT 42.0dBA @ 1.5 m (4.9 ft) FRONT 45.0dBA @ 1.5 m (4.9 ft) 9.2 Thermal Performance The Te25xh is designed to supply power from three 650W rectifiers plus one additional for n+1 (four modules in total) when operating at an ambient temperature of 46°C (114.8°F). Argus Technologies Ltd.
10 Maintenance Although very little maintenance is required with Argus systems, routine checks and adjustments are recommended to ensure optimum system performance. Qualified service personnel should do repairs. The following table lists a few maintenance procedures for this system. These procedures should be performed at least once a year. WARNING: HIGH VOLTAGE AND SHOCK HAZARD. Use extreme care when working inside the enclosure/shelf while the system is energized.
11 Argus Conventions 11.1 Numbering System Argus Technologies uses an eight-digit drawing number system, which is broken into three blocks. The first three digits describe the category of the product; e.g., rectifier or fuse panel. The next three digits indicate the sequence in which the product number was allocated in a particular category.
REVISIONS KO SIZES 1 @ 1" 1 @ 3/4" 2 @ 1/2" TYP. 2 PLACES SEE 029-006-08 FOR DETAILS 26.4 671 LTR DESCRIPTION B UPDATED WITH REVISED PARTS C UPDATED: REVISED DOCUMENTATION VED 2007/04 VED D GENERAL UPDATE 2007/12 REV BY DATE VED APPD 2006/06 ME VED 28.8 731 21.4 544 5.8 148 2.7 70 38.5 977 35.2 893 2.5 64 18.4 467 15.2 387 14.4 367 2.5 64 2.5 64 3.2 83 2.8 72 21.2 537 20.1 511 15.
REVISIONS DESCRIPTION LTR 26.4 671 REV BY DATE APPD 28.8 731 AC LOAD CENTER 26.4 671 28.8 731 AC LOAD CENTER 38.5 977 MAIN BREAKER DISCONNECT BOX FRONT VIEW 38.5 977 OPTION 1 SIDE VIEW AC SURGE PROTECTOR 12.6 319 MAIN BREAKER DISCONNECT BOX 34.8 884 FRONT VIEW COMBINATION METER SOCKET W/ MAIN BREAKER SIDE VIEW AC SURGE PROTECTOR OPTION 2 CONBINATION METER SOCKET W/ MAIN BREAKER 42.
REVISIONS AC POWER MAIN/ SERVICE ENTRANCE HUB LTR DESCRIPTION REV BY DATE APPD B UPDATED WITH REVISED PARTS VED 2006/08 EOF C GENERAL UPDATE VED 2007/12 * OPTIONAL SIDE AND BOTTOM KOs ENTRY AVAILABLE (NOT SHOWN) AC LOADCENTER AC SURGE PROTECTOR REAR CONDUIT ENTRY KOs (FOR DC POWER, ALARM & TELCO WIRING ACCESS) 1 @ 1" TRADE SIZE KO 1 @ 3/4" TRADE SIZE KO 2 @ 1/2" TRADE SIZE KO TYP.
REVISIONS REV BY DATE APPD B REDESIGNED VED 2007/11 ME C NEW ITEMS 21, 22, 23 AND 24 VED 2007/12 LTR DESCRIPTION KIT PARTS LIST: 2 14 10 3 PLACES 6 PROVIDED BY ARGUS: ITEM 1: ASSY POLE MOUNT BRACKET, QTY. 1 REQ'D ITEM 2: HOOK BRACKET, QTY. 1 REQ'D ITEM 6: SCREW, 3/8-16 x 1", HEX HEAD, QTY. 3 REQ'D ITEM 7: SCREW, 1/4-20 x 1", HEX HEAD, QTY. 6 REQ'D ITEM 9: 1/4" LOCK WASHER, QTY. 6 REQ'D ITEM 10: 3/8" WASHER, NEOPRENE BONDED, QTY. 3 REQ'D ITEM 11: 1/4" FLAT WASHER, QTY.
REVISIONS LTR REV BY DESCRIPTION DATE APPD INSTALLATION INSTRUCTIONS: STEP 1: UNDO EXISTING HARDWARE (ITEMS 6, 10 AND 14) ON THE BACK OF ENCLOSURE. INSTALL HOOK BRACKET (ITEM 2) AS SHOWN RE-USING REMOVED HARDWARE, OR THOSE SUPLLIED IN KIT. STEP 2: DRILL PROPERLY SIZED HOLES IN POLE TO INSERT RODS (ITEM 8) THROUGH AS SHOWN. PLEASE NOTE THAT POLE MOUNTING HARDWARE IS PROVIDED BY CUSTOMER. STEP 3: ADJUST RODS TO ACCOMMODATE BRACKET AND HARDWARE. PRE-INSTALL WASHER AND NUT (ITEM 12 & 13) ON REAR OF RODS.
REVISIONS LTR B 2 PLACES 2 1 DESCRIPTION ADDED PARTS LIST REV BY DATE VED 2007/12 APPD KIT PARTS LIST: 2 PLACES ITEM 1: RISER SIDE PIECE ITEM 2: RISER PLATE ITEM 3: 1/4-20 HEX HEAD SCREW ITEM 4: 1/4-20x1" SECURITY SCREW ITEM 5: 1/4-20x3/4" SECURITY SCREW ITEM 6: 1/4-20 PHILLIPS HEAD SCREW ITEM 7: 1/4-20 FLAT WASHER ITEM 8: 1/4-20 LOCK WASHER NOTE: ALL HARDWARE IS SS MATERIAL 6 7 Te25 ENCLOSURE SHOWN FOR ILLUSTRATIVE PURPOSES ONLY. IT IS NOT PART OF THE KIT.
REVISIONS DESCRIPTION LTR 14.200 360.68 REF. REV BY DATE APPD B ADDED ITEM 3; ADJUSTED INSTALL INSTRUCTIONS VED 2007/09 SG C ADDED NEW ITEM 5 VED 2007/11 ME D ADDED PARTS LIST VED 2007/12 3 2 PLACES 9.800 248.92 REF.
REVISIONS LTR DESCRIPTION REV BY DATE B ADDED Te25 DETAIL ON PAGE 3 VED 2007/12 APPD 2 2 PLACES 11 18 1 17 18 26 2 PLACES STEP 1: LADDER BRACKET ASSEMBLY 1. Unpack and inspect the ladder bracket for any damage. Verify that all the required hardware is included. 2. Attach Item 1 to Item 2 using 3/8"-16 hardware provided (Items 11,17, 18 and 26) as shown. Torque screws to 20 ft/lbs.
REVISIONS LTR REV BY DESCRIPTION DATE APPD 11 18 18 17 2 PLACES REF 26 STEP 2: LADDER BRACKET INSTALLATION W/ PLATFORM STYLE POLE MOUNT BRACKET 1. Install ladder bracket below enclosure by aligning obround holes with holes in bottom pole mount bracket. 2. Use 3/8"-16 hardware (Item 11,17,18 and 26) to bolt together as shown. Ensure the position of the ladder bracket is adjusted to properly grip the pole. Torque screws to 20 ft/lbs. 3.
REVISIONS LTR DESCRIPTION REV BY DATE APPD Te25 ENCLOSURE Te25xh ENCLOSURE POLE MOUNT BRACKET POLE MOUNT BRACKET LADDER BRACKET BOTTOM ISOMETRIC VIEW LADDER BRACKET BOTTOM ISOMETRIC VIEW THESE DESIGNS AND SPECIFICATIONS ARE THE PROPERTY OF ARGUS TECHNOLOGIES AND SHALL NOT BE COPIED OR USED FOR MANUFACTURING WITHOUT ITS WRITTEN CONSENT.
REVISIONS LTR B DESCRIPTION GENERAL UPDATE REV BY DATE VED 2007/11 APPD 1 A B 7 BOTTOM ISOMETRIC VIEW STEP 2 BOTTOM ISOMETRIC VIEW STEP 1 ISOMETRIC VIEW STEP 3 NOTES: SEE NOTES 4 SEE NOTES 4 DETAIL A SCALE 1 : 5 TYP. 4 PLACES 5 6 DETAIL B SCALE 1 : 5 TYP 4 PLACES THESE DESIGNS AND SPECIFICATIONS ARE THE PROPERTY OF ARGUS TECHNOLOGIES AND SHALL NOT BE COPIED OR USED FOR MANUFACTURING WITHOUT ITS WRITTEN CONSENT.
This page intentionally left blank.
Service Centers Factory Service Centers Canada and International Argus Technologies Ltd. ATTN: RMA Returns 7033 Antrim Avenue Burnaby, BC, V5J 4M5 Canada Tel: +1 604 436 5900 Fax: +1 604 436 1233 Email: returns@argusdcpower.com USA Argus Technologies Inc. ATTN: RMA Returns 3116 Mercer Avenue Bellingham, WA, 98225 USA Tel: +1-360 756 4904 Fax: +1-360 647 0498 Email: returns-usa@argusdcpower.com Asia-Pacific PCM Electronics (Dong Guan) Co., Ltd.