User's Manual
Table Of Contents
- Preface
- Contents
- 1 Introduction
- 2 Safety requirements
- 3 Installation prerequisites
- 4 iRU4438 iRRH installation overview
- 5 Installing the iRU4438 iRRH
- 5.1 Assembling cables
- 5.2 Routing pre-assembled power/fronthaul Ethernet/grounding cables
- 5.3 Installing RF antennas on upper/lower omni-antenna brackets
- 5.4 Installing RF antenna cables
- 5.5 Installing the iRU4438 iRRH mounting bracket
- 5.6 Hoisting the iRU4438 iRRH on elevated structures
- 5.7 Installing the iRU4438 iRRH on the mounting bracket
- 5.8 Connecting the grounding cable
- 5.9 Connecting the fronthaul Ethernet cables
- 5.10 Connecting the 110/220 V ac power cable
- 5.11 Checking power
- 5.12 Installing the solar shield
- 6.13 Terms, Acronyms and Abbreviations
Installing the iRU4438 iRRH
5-10 iRU4438 iRRH Product Descripton and Installation Guide
lines lift and guy points. The carabiners must be ≤ 3/8 in (≤ 9 mm) and sized to
safely lift the load of the iRRH.
The hoist line lift point for the iRRH is shown in Figure 5-10. The tag line guy point for
guiding and limiting any rotation of the iRRH while lifting is shown in Figure 5-11.
DANGER
The Operator is responsible for determining the method of hoisting the
iRU4438 iRRH into position on elevated structures. Be sure to follow all
established Operator procedures safety precautions when hoisting the
equipment on elevated structures.