Installation guide
BreezeNET
®
B130/B300 GigE Quick Installation Guide
- 5 -
P/N: 215743 July 2010
Antenna, ODU, IDU installation.
Installation guidelines
1. Install the antenna in the appropriate location (see antenna alignment instructions below).
Antenna’s position must be lower than the highest antenna pole point at least by 2 antenna
heights. Point the antenna to the required direction. Provide antenna grounding. (In case of
using ODU with external antenna).
2. Connect RF cable to the antenna. Twist the connector tightly. Seal the connector. (In case
of using ODU with external antenna).
3. Install ODU having its connectors pointing down and tighten it. Appropriate place for ODU
installation is as close as possible to the antenna but reachable for you to connect ODU via
its console port. Provide ODU grounding.
In case of using ODU with integrated antenna:
Install ODU according to the direction required for the link. Do not tighten it too hard unless
the integrated antenna alignment is not complete. Install ODU connectors down. Provide
ODU grounding.
It is extremely important to install ODU connectors down!
4. Connect RF cable to the ODU previously having touched RF cable connector case with
ODU connector case for removing static electricity on the ODU. Seal the connector (in
case of using ODU with external antenna).
5. Connect the STP/FTP Service (ODU-to-IDU) cable to the ODU. Seal the ODU connector.
6. Lay the STP/FTP Service cable “from top to bottom” – from ODU to IDU. Provide cable
whipping before entering the building. Whipping radius should be at least 10 times
STP/FTP cable diameter.
7. If Service cable connector for IDU hasn’t been installed, install it. Seal the connector.